The total time given for the construction of a job is 6 months. The framing is given 2 months to complete. The framing will only take 1 month to complete. What is the amount of float time that is available for the framing?

Get ready for the Contractors Business and Law Exam. Enhance your study experience with flashcards and diverse multiple-choice questions. Each question is designed with hints and thorough explanations to boost your readiness for success!

To determine the amount of float time available for the framing in this construction scenario, we first need to look at the total time allotted for the entire project and the specific time allocated for the framing task.

The total duration for the entire construction job is 6 months, and the framing is scheduled to be completed within 2 months. However, if the framing can actually be finished in just 1 month, this creates a scenario where there is extra time, known as float or slack time, available for that task.

Float time is the amount of time that a task can be delayed without delaying the subsequent tasks or the overall project schedule. In this case, since the framing is only taking 1 month to complete but has a tolerance of 2 months, the difference between these two durations gives us the amount of float available.

Calculating the float time:

  • Allocated time for framing: 2 months

  • Actual time required for framing: 1 month

Float time = Allocated time for framing - Actual time required for framing

Float time = 2 months - 1 month = 1 month

Therefore, the amount of float time available for the framing is indeed 1 month. This means that the framing contractor can take